- The council approved CORE Construction Services of Texas for the police training center on Nov. 9.
- The project budget is capped at $42 million; $42,000 covers early design-phase work.
- The sign code rewrite, including a ban on new pole signs, returns Jan. 11, 2027.
PLANO, Texas (Nov. 16, 2026) The Plano City Council on Monday, Nov. 9, hired CORE Construction Services of Texas as construction manager for a new police training center, with the project capped at $42 million, according to Community Impact and the city's posted meeting record.
Only $42,000 was approved for now, for pre-construction work, city staff told the council, Community Impact reported. The new building of about 33,000 square feet will replace the current 21,904-square-foot training facility on 14th Street, which was built in 1990. Voters approved the project in the May 2025 bond election.
The council also held a public hearing on a rewrite of the city's sign rules and then tabled it until its Jan. 11, 2027, meeting, according to the meeting record and Plano Weekly. The rewrite would ban new pole signs and bar illuminated signs within 300 feet of homes; speakers warned that rule could leave hospital, church and business signs hard to see at night.
A companion ordinance on temporary signs was tabled to the same date, and an item to sell city land at K Avenue and 15th Place was pulled from the agenda, Plano Weekly reported.