Roads · Austin · Southeast & Del Valle

William Cannon Drive work near McKinney Falls Parkway is pushed into 2027

The Southeast Austin corridor project between Running Water Drive and McKinney Falls Parkway had been due this fall and now targets early 2027.

BOLO Newsroom ·

Fact graphic for William Cannon Drive corridor: Segment: Running Water Dr. to McKinney Falls Pkwy.; Was due: Fall 2026; Now: Early 2027; Work: Signals, paths, drainage, utilities.
BOLO graphic of William Cannon Drive corridor, built from the sources listed with this story.
  • The project runs on William Cannon Drive from Running Water Drive to McKinney Falls Parkway.
  • The city's project page now shows substantial completion in early 2027.
  • The work adds shared-use paths on both sides of the road, signal upgrades, drainage and utility work.

AUSTIN, Texas (Nov. 22, 2026) The William Cannon Drive corridor project in Southeast Austin will not finish this fall, and the city now expects substantial completion of the section in early 2027, according to the city's project page and FOX 7 Austin.

The work runs from Running Water Drive to McKinney Falls Parkway. The city lists roadway and intersection improvements, traffic signal upgrades, shared-use paths on both sides of the road, median reconstruction, drainage improvements and utility work.

In a statement to FOX 7, Austin Transportation and Public Works cited unknown underground utilities at the McKinney Falls Parkway intersection, private developments building next to the work area and heavy rain this year. The department said the added cost of the delays has not been finalized.

The city says completion dates can change as work continues and posts updates on its project page. Drivers heading to McKinney Falls Parkway during the morning rush should plan for extra time.

Sources